Authorisation Process for Distributed Generation Systems
The authorisation process allows individuals or organisations to legally install and operate a distributed generation system (e.g., rooftop solar) connected to the electricity distribution network.
1
Application Submission
Submit the application form prescribed under the Licences and Authorisation Regulations, 2024 to the Commission.
Once submitted, the Commission issues a unique registration number and sends an acknowledgement receipt electronically.
2
Application Review & Technical Feasibility
The Commission processes the application within 3 months of the acknowledgement date.
The application is forwarded to PUC to conduct a technical feasibility study, to be completed within 60 days.
If feasible, PUC informs the Commission, which then notifies the applicant.
The Commission issues a certificate to install the system.
3
If Issues Are Found
If PUC identifies problems, it notifies the applicant and the Commission within 25 days.
The applicant has 15 days to correct the issues and inform PUC.
PUC reassesses:
If resolved: process continues.
If unresolved: application is unsuccessful.
If found technically unfeasible, the applicant is notified within 22 days, and the application is placed on a priority waiting list.
4
Installation
Installation must comply with BS 7671 standards and be completed within 180 calendar days of receiving approval.
If installation is not completed in time, the application fails unless:
The applicant has received an approved extension from PUC, or
The installation is completed on time and PUC is notified.
5
Commissioning for Systems up to 100 kW (Net Billing)
Applicant submits the work completion report to PUC.
PUC performs inspection and safety checks within 7 working days.
If issues arise: Applicant has 7 working days to fix and resubmit.
If approved, PUC:
Synchronises the system with the grid
Installs meters
Issues a synchronisation letter and commissioning date
Sends a copy to the Commission
6
Commissioning for Systems 100 kW to 500 kW (Gross Metering)
Applicant consults with PUC to agree on grid impact evaluation, metering arrangements, and any additional requirements.
PUC provides required forms and export electricity rates.
After installation, applicant submits the work completion report to both the Commission and PUC.
The Commission inspects the system within 7 working days.
If successful: a safety certificate is issued within 5 working days.
The safety certificate must be submitted to PUC within 3 working days.
PUC, within 7 working days, will synchronise the system, install meters, and issue a commissioning letter.
✅ Once all steps are successfully completed and conditions met, the Commission issues the authorisation to operate the distributed generation system.